Posted on: September 21, 2018

Tollway Expansion Construction Update!

Illinois Tollway Logo

TOLLWAY CONSTRUCTION NEWS -- UPDATED 1/14/19:

Roof removal on the over-the-road pavilion structure at the O’Hare Oasis on the Tri-State Tollway (I-294) is scheduled to begin this week. The O’Hare Oasis fuel stations and convenience stores operated by 7-Eleven remain open to provide services for both northbound and southbound travelers along I-294. 

Beginning this week, workers are scheduled to begin disassembling the roof and removing sections of it from inside the building. Traffic is shifted to safely accommodate this work. As the roof is removed, workers will also begin the process of removing the windows. The pavilion will be wrapped in a thick mesh curtain wall, which will prevent any debris from landing on the roadway below while the windows are removed inward through the interior of the structure. 

On I-294, temporary overnight closures will be needed for the removal of the pavilion windows. Once removal of the over-the-road portion of the building is complete, work will continue into the spring to take down the remaining portions of the building and the bridge structure. Overnight lane closures, including temporary full closures on I-294, will be scheduled as needed.

Following removal of the over-the-road pavilion, the O’Hare Oasis parking lots will be restored. The work is scheduled to be complete in 2019.

A full press release can be viewed by clicking here.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 1/9/19:

The Tollway has submitted a memo on soundwalls in the Village for your review. Please click here to view the short memo which contains information about new soundwalls in two locations and replacement soundwalls in other locations. There is a wealth of information about the Central Tri-State Tollway reconstruction project on the Tollway website (including a very detailed sound study and other relevant materials such as construction alerts) - please click here to go to their project website.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 12/13/18:

The Tollway has let the Village know that they have 15 minute trooper assisted full stops scheduled on SB Irving Park Rd Ramp to Irving Park Plaza 33 for the evening of 12/17. There are 8 full stops scheduled from 12 am to 4 am, and each stop will last 15 minutes. Their contractor will be working on removing the temporary light poles.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 12/12/18:

There will be temporary lane closures on Irving Park Road on Thursday 12/13 to stripe the pavement. Temporary closures in each direction will last from 9 AM to 3 PM, weather permitting.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 11/28/18:

Surveyors for the Illinois Tollway will be out on Monday, December 3rd to stake properties within the Village that are impacted by the Central Tri-State project.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 11/21/18:

The Village would like to provide you with an update on the project on the Central Tri-State Tollway (I-294) from O’Hare Oasis to Balmoral Avenue, which includes reconstruction of the inside shoulders and center barrier wall.

The Tollway is wrapping up a large portion of the work in this section of I-294, and they are now in winter configuration. You’ll continue to see some barrels and barrier wall in work zones on the shoulder as they start to slow work for the winter, but all lanes are open to traffic, and both Irving Park Road ramps to northbound I-294 are now open.

There will continue to be off-peak temporary lane closures throughout December to continue work, and construction in this area will resume in spring 2019.

All lanes on local Lawrence Avenue will remain open through the holiday. The Tollway anticipates that the barrels will be reinstalled the following week to complete the remaining work on the local road.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 11/2/18:

There will be lane closures in both directions on Irving Park Road under I-294 for protective shield work. These temporary daytime closures will be in place from 9:00 AM to 3:00 PM on 11/5 - 11/11, weather permitting.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 10/31/18:

Traffic in both directions on Irving Park Road is scheduled to be reduced to a single lane from 9 a.m. to 3 p.m. daily through Sunday, November 4, for bridge work.

The work on I-294 is progressing. Some full stops are anticipated overnight on I-294 from the O’Hare Oasis to the O’Hare Interchange for aerial cable work. Weather and conditions permitting, overnight on 10/31 into 11/1 there will be full, trooper assisted closures scheduled in fifteen minute increments on I-294 in both directions from 1:15 AM to 2:30 AM.\

The three full fifteen-minute closures are scheduled for 1:15 AM, 1:45 AM and 2:15 AM.

I also want to mention the following lane closures will be occurring overnight on 10/31, weather permitting, for aerial cable work:


8:00 PM - 10:00 PM: 1 left lane closed in each direction

10:00 PM - 1:00 AM: 2 left lanes closed in each direction

1:00 AM - 4:00 AM: 3 left lanes closed in each direction


These will be on I-294 from O’Hare Oasis to the O’Hare Interchange (milepost 40.2).


TOLLWAY CONSTRUCTION NEWS -- UPDATED 10/25/18:

Some overnight lane closures are occurring on I-294 from Irving Park Road to Balmoral Avenue.

On the night of Thursday, October 25th, weather permitting, the following lane closures will be in place:


8:00 PM - 11:00 PM: 1 left lane closed in each direction

11:00 PM - 1:00 AM: 2 left lanes closed in each direction

1:00 AM - 4:00 AM:   3 left lanes closed in each direction


There will also be closures on the ramp from Balmoral Avenue to SB I-294 from 8:00 PM -11:00 PM.

Also scheduled for early morning on 10/26 are trooper assisted full stops occurring this week to provide a safe work zone for aerial cable work:

On I-294, fifteen minute full closures in both directions are scheduled for 1:00 AM and 1:30 AM.

On Balmoral On-Ramp, fifteen minute full closures are scheduled for 2:00 AM, 2:30 AM, 3:00 AM and 3:30 AM.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 10/23/18:

Work on I-294 is progressing. We would like to let you know of some full stops that are anticipated overnight on local Irving Park Road due to bridge work on the Central Tri-State. Contractors will be working on removing bridge beams, weather and conditions permitting. Local Irving Park Road will have right lane closures in both directions from 10 PM on the night of Tuesday 10/23 into 5 AM on Wednesday 10/24, weather permitting. There will be two trooper assisted full stops where traffic will not be able to get through at 3:00 AM - 3:15 AM and at 3:30 AM - 3:45 AM on that night.


TOLLWAY CONSTRUCTION NEWS -- UPDATED 9/24/18:

The I-294 (from the Oasis to Balmoral) traffic switch is tentatively scheduled for this week, weather and conditions permitting. For the section north of Irving Park to Balmoral Avenue, the southbound traffic shift is scheduled for the night of September 26, and the northbound traffic shift from Balmoral Avenue to Irving Park is scheduled for the night of September 27. The traffic switch for the section south of Irving Park is tentatively scheduled for the following week.

Please note that this traffic shift will be split into two 2-lane configurations. There will be local lane access in the right two lanes, and express lanes in the left two lanes. The work zone will be closed off by a barrier zone in between the lanes in both directions. Signage will alert motorists to the new traffic pattern.